Chairman of the Board of Samruk-Energy, Kairat Maxutov, conducted on-site meetings at Ekibastuz SDPP-1, Ekibastuz SDPP-2, and Bogatyr Komir LLP.
During his visit, Maxutov inspected the progress of the restoration works on Unit 1 at Ekibastuz SDPP-1 and received updates on the performance during the autumn-winter period, as well as the modernization of Unit 3. Subsequently, he chaired another meeting of Samruk-Energy's Investment and Innovation Council to discuss the reconstruction and modernization of the fuel supply production complex.
At Ekibastuz SDPP-2, Maxutov was briefed on the progress of the autumn and winter period (AWP). The heating season at both Ekibastuz SDPP-1 and Ekibastuz SDPP-2 is proceeding smoothly, with surplus fuel reserves. Discussions during the meeting covered planned repair works for 2024 and the progress of the project to expand and reconstruct ESDPP-2 plant with the installation of third and fourth generating units.
At Bogatyr Komir LLP, Maxutov received updates on the implementation of projects for cyclic-flow coal mining technology and cyclic-flow overburden complex. Additionally, discussions focused on the future development of coal sales markets.