First Deputy Prime Minister Nurlуbek Nalibayev visited several major energy and industrial projects in Turkestan region, as well as social and infrastructure facilities.
In his Address to the Nation, President Kassym-Jomart Tokayev set the goal of securing a stable surplus of electricity by 2029. Achieving this goal will require substantial investment in new generating capacity, which is essential to strengthening Kazakhstan's energy independence.
At the 1,113.4 MW Turkestan combined-cycle gas turbine power plant under construction in Sairam district, Nalibayev stressed the project's importance for the country's power sector. Once completed, the plant will help ease electricity shortages in southern Kazakhstan, increase the country's generating capacity and provide consumers with a more reliable power supply.
A total of 2,455 people are working at the site: 2,281 on the day shift and 174 on the night shift.
The main equipment, including gas turbines, steam turbines and heat recovery steam generators, has been delivered to the site. All four Siemens gas turbine units have been installed. Construction and installation work is 62% complete, electrical network installation is 96% complete, and the gas pipeline has been completed.
The project includes seven wells. Two are currently producing a total of 960 cubic meters of water per day, while 240 cubic meters per day will be needed to bring the plant's first phase into operation.
A 3.1-kilometer access road has also been completed and opened for use.
"This is an important facility that is under the direct oversight of the Head of State. Construction must not be delayed, and the work must be completed on schedule. You said that the first unit would undergo a test run by the end of this year, with 382 MW of generating capacity to be connected to the power system in May 2027 and a further 382 MW in August. This means that 764 MW is expected to be brought online by September. We need to pick up the pace further. We should consider bringing forward the current March–May 2028 deadlines, accelerating the project and having the plant operate at full capacity by the end of 2027. Once operational, this major plant will be able to supply electricity to the region, the city of Shymkent and Zhambyl region. The pace of construction has clearly improved significantly. At the beginning of the year, the project was only 15% complete; it has now reached 62%. The Government and the akimat are providing comprehensive support. Your responsibility is to organize the work properly and meet the commitments you have made", - the First Deputy Prime Minister said.
Nalibayev then visited the Sastobe Innovation Complex in Tulkubas district, a major investment project that will expand the region's chemical industry and produce goods currently sourced from imports. Once fully operational, the complex is expected to produce 400,000 tonnes of lime, 100,000 tonnes of caustic soda, 120,000 tonnes of polyvinyl chloride (PVC), 200,000 tonnes of calcium carbide and 1 million tonnes of cement annually.
A lime production line was commissioned last year. Its output is now supplied to domestic metallurgical companies and manufacturers of construction materials.
The launch schedule for the remaining phases of the investment project has been revised to reflect funding availability, and the various aspects of its implementation have been reviewed in detail. The relevant government agencies have been instructed to identify sources of funding, complete the construction of engineering infrastructure and keep the project on schedule.

















































