At the energy facilities of "Samruk-Energy" JSC, the repair campaign for the autumn-winter period is in full swing.
To ensure stable and uninterrupted energy and heat supply, Samruk-Energy group has planned 116 repairs on 104 pieces of equipment.
To date, almost 50% of the planned repairs have been completed.
Repaired units include power units No. 2, 5, 7, 8 at Ekibastuz SDPP-1, turbine No. 1 at Ekibastuz TPP, boilers No. 9, 10, 13, turbine No. 8, 5 hot water boilers at Almaty CHP-1, boilers No. 2, 4, 8, turbines No. 1, 3, 4, 6 at Almaty CHP-2, boilers No. 1, 2, 3, turbines No. 2, 3 at Almaty CHP-3, and others.
More than 20 units of equipment are currently under repair, including power unit No. 6 at Ekibastuz SDPP-1, power unit No. 1 at Ekibastuz SDPP-2, 5 boilers at Ekibastuz TPP, 4 of which are undergoing major repairs.
The repair campaign is proceeding according to the approved schedule.