The Project "Reconstruction of cable grids in Almaty"

 photo12 AJK podstanc

Project Purpose:

Reducing the level of wear and tear of power grids.

Reconstruction, modernisation and new construction in order to increase transformer capacity and cover the capacity deficit for new and existing consumers.

Reconstruction of power grids with replacement of overloaded and expired cable networks not requiring connection of new consumers in order to increase reliability of power supply and reduce technological failures.

Description of the project:

The total number of 10-6-0.4kV cable lines across Almaty is 4,424 km. According to GOST, the service life of power cables is 30 years.

Currently, 2,478.76 kilometres of 10-6-0.4kV cable lines in Almaty or 56% of the total volume of cable lines have service life of more than 30 years.

In general, 948 kilometres of cable lines in Almaty have service life over 50 years.

Worn-out lines lead to an annual increase in the number of accidents and frequent interruptions in power supply, which leads to under-supply of electricity and additional costs for emergency recovery work. The main causes of damage are ageing of insulation, breach of tightness, corrosive deterioration of cable sheathing.

Within the framework of this project it is planned to carry out measures on reconstruction of cable networks 10-6-0,4kV for the total amount of 83 300 000 thousand tenge excluding VAT with the total volume of reconstruction of networks about 933 km.

Status:

Construction and installation works are being carried out on 11 objects having DED with the length of 267 km.   Adjustment of the design and construction plans for 4 objects is underway.

Implementation terms: 2022-2030.

Operation: 2024-2030.

Planned activities:

Phased design and construction and installation works 2023-2030.

Project "CONSTRUCTION OF COUNTERREGULATING KERBULAK HPP ON THE ILI RIVER"

photo8 Kerebulak GES 

The project goal: Creation of a reservoir-counter-regulator in the downstream of the Kapshagay HPP to equalize uneven weekly-daily releases of the Kapshagay HPP and transfer of Kapshagay HPP to the mode of covering peak loads using all available capacity in Almaty energy system and in South energy zone of Kazakhstan., which experience shortage in capacity and energy.  

Improvement of environmental situation in the lower reaches of the Ili River by applying a uniform regime of daily releases from the reservoir-counter-regulator.

Implementation period: 2021-2026

The project description:

  • Increase by 110 MW of the regulating capacity of the Kapchagay HPP;
  • Generation of additional volumes of electricity at the Kerbulak HPP;
  • Income from the sale of the regulating capacity of the Kapshagay HPP in the amount of 110 MW

Status.

At present, the activities on the development of the Project’s FS and obtaining a tariff that secure the project’s payback, is underway.

Project "Reconstruction and modernization of the Cascade of HPPs of "APP" JSC

photo4 KASKAD GES

The project description: Replacement of obsolete and worn-out equipment for reliable energy supply of consumers with electricity and maximum use of Big Almaty river’s energy capacity.

The project goal:

  • increase in installed capacity by 7,5 MW;
  • increase in electricity production by 41,7 mln. kWh annually;
  • ensuring the reliability and safety of operation of the HPP Cascade;
  • owing to an increase in electricity generation by the HPP Cascade, combustion of energy resources (coal, gas, etc.) by thermal power plants will reduce;
  • providing consumers of Almaty city and Almaty region with reliable and uninterrupted supply of electricity in accordance with load schedules.

The project implementation period: 2022-2027

The project "EXPANSION AND RECONSTRUCTION OF EKIBASTUZ SDPP-2 WITH THE INSTALLATION OF POWER UNIT No. 3"

photo7 GRES 2

The project goal: Increasing the plant's installed capacity by 636 MW for reliable power supply to the Republic of Kazakhstan сonsumers.

The project description:

Improving the reliability of energy supply to industry, residential sector, and the population of the Republic of Kazakhstan, increasing the export potential, increasing the energy security and energy independence of the country.

Implementation period: 2010-2025

Status.

Currently, arrangements for delivery of equipment stored in China are underway. At the same time, the measures on receiving a tariff that ensures the payback of the project are taken;, an application for receiving an individual tariff was submitted to the RK Market Council on January 28, 2022.

Planned activities:

Sign an investment agreement with the RK ME

Complete delivery of the equipment

Attract debt financing

Construction and installation works

Project "Reconstruction of the Almaty CHP-3 based on CCGT unit with an increase in the plant’s capacity up to 450 MW"

photo3 TES 3

The project goal: The project "Reconstruction of the Almaty CHP-3 based on CCGT unit with an increase in the station's capacity to 450 MW" is implemented in accordance with the roadmap for a comprehensive solution of environmental issues in Nur-Sultan and Almaty cities.

The project description: Reconstruction of the Almaty CHP-3 including construction of  450 MW CCGT unit to partially cover the shortage of maneuvering capacities in the southern zone of Kazakhstan. In order to provide consumers of Almaty city and Almaty region with a reliable and uninterrupted supply of electricity and heat in accordance with load schedules and temperature conditions.

Implementation period: 2021-2024

Status: Public hearings on the results of the Preliminary Environmental Impact Assessment as part of the Project’s FS were held as open meeting on January 14, 2022. A feasibility study is under development. The project’s FS considers the use of GTP + RB and / or 450 MW CCGT including the ability to operate in a maneuverable mode.

To ensure the completion of the construction of the new station at the ACHP-3 site, in December 2024, “AlES” JSC plans to conclude an EPC contract. The conclusion of the EPC contract is planned through an open international two-stage tender by holding a reversed auction.

The Project "Modernization of Almaty CHP-2 including reduction of environmental footprint"

photo1 TES 1

The project goal: Reducing the negative environmental impact of Almaty CHP-2 on the environmental situation in Almaty city by transfer the station to firing natural gas. In order to provide consumers of Almaty city and Almaty region with a reliable and uninterrupted supply of heat and electricity in accordance with load

The project description: Construction of the new station using gas turbine technologies with a capacity of up to 600 MW at the site of Almaty CHP-2. The project is implemented to execute the instructions of N.A. Nazarbayev, the First President of the Republic of Kazakhstan – Elbasy No. 17-01-7.8 dated September 20, 2017, as well as in pursuance of the order of Tokayev K.K, the President of the Republic of Kazakhstan dated July 10, 2021 to ensure the construction of the new combined cycle gas turbine unit at Almaty CHP-2 with commissioning in December 2023.

Implementation period: 2022-2026

Financing:

"Samruk-Energy" JSC conducts negotiations and carries out preparatory activities for arranging of financing. As of today, arranging of financing with the European Bank for Reconstruction and Development (hereinafter - the EBRD) is considered in detail.

As part of the ongoing work, the EBRD is dealing with detailed study of the Project at a level sufficient to make a decision on its possible financing.

EBRD consultants conducted An Environmental and Social Impact Assessment and submitted a report that includes the following materials:

  1. Environmental and Social Action Plan for Modernisation of CHP 2;
  2. Non-Technical Summary;
  3. Resettlement Framework;
  4. Stakeholder Engagement Plan;
  5. Report on possible Environmental impacts.

Status: A positive conclusion on FS of the project was received from RSE "Gosexpertiza" on December 30, 2021.

To ensure the completion of the construction of a new station at the ACHP-2 site within the planned time frame, “APP” JSC plans to conclude an EPC contract with an individual plan for the phased development of design and estimated documentation and obtaining an approval from an authorized body with the support of experts.

The implementation of the Project jointly with the EBRD, exclusively based on an open international two-stage tender, ensures transparency, and obtains the most competitive final cost.

The Project "Expansion of Almaty CHP-1 with the construction of 200-250 MW CCGT unit"

photo1 TES 1

The project implementation goal: Expansion of  Almaty CHP-1 with the construction of 200-250 MW CCGT unit to ensure the reliability of heat and electricity supply to Almaty city.

The project description: To provide consumers of Almaty city and Almaty region with a reliable and uninterrupted supply of electricity and heat in accordance with load schedules and temperature conditions, it is planned to increase the capacity from 145 MW to 200-250 MW. The final capacity and cost of the Project will be determined after considering the results of the feasibility study.

Implementation period: 2021-2024

Status: Public hearings on the results of the Preliminary Environmental Impact Assessment as part of the Project’s FS were held as open meeting on February 22, 2022. Currently, the work on the development of the project’s feasibility study. The development of the FS is scheduled to be completed in June 2022.

To ensure the completion of the construction of a new plant at the ACHP-1 site in December 2024, “APP” JSC plans to conclude an EPC contract. The conclusion of the EPC contract is planned to be concluded on the basis of an open international two-stage tender by holding a reversed auction.